All Saints Update – May 2022
Roofing works have generally progressed well in the last month, with tiling to the main roof and side aisles approaching completion and guttering being prepared for installation. There has been a delay to the [...]
Roofing works have generally progressed well in the last month, with tiling to the main roof and side aisles approaching completion and guttering being prepared for installation. There has been a delay to the [...]
There has continued to be good progress with the roof in the last month. Tiling is largely complete on the main roof covering the nave, with felt and battening to the side aisles under [...]
ALL SAINTS UPDATE MARCH 2022 There has been good progress with the roof in the last month. The felt, battening and insulation over the nave is complete, and high level electrical cabling installed, with [...]
All Saints Update – February 2022 Work on the roof has progressed well during January and it is now mostly boarded in – the roof insulation is being applied and we hope that tiling [...]
ALL SAINTS UPDATE JANUARY 2022Much progress has been made with the roof in the last month, as can now be clearly seen from outside the church. The ‘glulam’ beams that will support the nave roof [...]
Work has continued to progress well during the last month. The limecrete slab, which forms the base for the underfloor heating, has now cured sufficiently to allow the erection of full internal ‘birdcage’ scaffolding. This [...]
Work has continued to progress well during the last month. The limecrete slab, which forms the base for the underfloor heating, has been laid and is now curing. Internal scaffolding has been erected at [...]
Work has progressed well during the last month. The old boiler room has been thoroughly cleaned of asbestos, brick cleaning is progressing, internal scaffolding has been erected at the eastern end of the church and [...]
Report on Site Meeting No 3 – September 6th 2021Work has steadily progressed during August - mainly on the inside of the church.Buxton’s reported that the completion date now was estimated to be late October [...]
During July work has continued on clearing the interior of the church, including the lifting and storage of the floor tiles, stripping out the old heating system and asbestos removal. Testing of cleaning methods for [...]