All Saints Church Update – January 2023
We are almost there! After 19 months of work on the site ‘practical completion’ is expected to happen before the end of January – this is the point at which the church ceases to [...]
We are almost there! After 19 months of work on the site ‘practical completion’ is expected to happen before the end of January – this is the point at which the church ceases to [...]
November saw good progress as the completion date draws near. Externally – the West Porch is well on its way having been held up by delayed delivery of special bricks and the weather [...]
There has been much progress on the site over the last month. The Rose Window installation is now complete and this has allowed work to resume on the West Porch – the external slabbing [...]
After 7 years of waiting, the iconic wheel window (also known as the Rose Window) returns to All Saints Church. The brand new window commissioned by the PCC and designed by Amanda Winfield has [...]
There has been good progress on the site over the last four weeks. Work on the new West entrance is well under way, with the opening formed through the wall [...]
During the month of August there was a great deal of progress – the internal painting is now finished except for the Rose window surround, the works to the Chancel outside are complete and [...]
The removal of internal and external scaffolding is now almost complete, the final section over the chancel will be taken away once the external eastern cross is reinstalled and the surrounding tiling is completed.An [...]
The main visible change over the last month has been the gradual removal of the external scaffolding – revealing the completed roof to the nave and side aisles. Work continues to complete tiling of the [...]
Roofing works have generally progressed well in the last month, with tiling to the main roof and side aisles approaching completion and guttering being prepared for installation. There has been a delay to the [...]
There has continued to be good progress with the roof in the last month. Tiling is largely complete on the main roof covering the nave, with felt and battening to the side aisles under [...]